Pentech Group Inc.
Home
www.pentechgroup.com
443.280.0442
skip to the main content area of this page
Home
Our Services
Management Profiles
Contact Us
Going Green
Home
Our Services
Management Profiles
Contact Us
Click here to learn more about the USGBC and LEED for Homes Certification ->
In the News !!!
Our new home was just featured in the November edition of North County News
Click here to read the news article ->
Building a LEED Platinum Home
The Step by Step Process
The Property "Before the Build"
The Plan
May 10th ... Building Permit Issued - Site Survey Complete
May 18th ... The Digging Begins
May 19th ... Digging Complete - Footers Going In
May 22nd ... The Concrete Walls Go Up
May 27th ... The Walls are Sealed and Backfilled
June 1st ... Where's Bob ?!?!?
June 3rd ... Basement Plumbing Rough In
June 15th ... Steel Supports & Concrete Slab Preping
June 17th ... Ready to Pour & "My New Hat"
June 22nd ... Finally ... The Pour Is Done
June 25th ... The Framing Begins (Almost)
June 26th ... The Framing Begins (Really)
Week of June 29th ... Framing (Week One)
Week of July 6th ... Framing (Week Two)
Week of July 13th ... Framing (Week Three)
Week of July 20th ... Roofing
July 27 - 28 ... Windows & Doors
July 29th ... Plumbing & HVAC Rough-ins
August 5th ... Fireplace Framing & Electrical Rough-in
Week of August 17th ... Front Porch & Deck Framing
August 24th ... Solar Panels !!!!!
August 25th ... Insulation (Sprayed Cellulose)
August 26th ... Fireplace Installation & Stone Prep
August 27th ... Insulation (Blown In)
August 28th ... LEED Pre-Drywall Inspection & Stone
Week of August 31th ... Inspection Follow-up & Stuff
September 5th ... Drywall
Week of September 8th ... Exterior Siding & Stuff
Week of September 14th ... Interior Trim & Stuff
Week of September 21st ... More Trim & New John Deere
September 30th ... BGE "On the Job" & Stuff
October 1st ... Front Door and Deck
October 5th & 6th ... Deck, Painters, Stone
Wednesday, October 7th ... A Very Busy Day
October 8th & 9th... Front Cedar & More Wells
Finishing the Wells
BGE, Garage Doors, Connecting the Wells
Week of October 19th ... Steps, Stone, and Screws
Week of October 26th ... Wood Floors and More
November 1st ... Floors, Geothermal, ERV, and Stone
November 3rd ... A very successful day
Week of November 9th ... Tile, vanities, etc.
November 16th ... Regrading the Property
November 18th ... Crunch Time ... Lots of Action
Finishing the Stone Fireplace
Ice Stone Countertops Installed
November 23rd ... "All Hands on Deck"
Sanding and Finishing the Floors (First Coat)
Finishing the Floors (Second Coat) and Stuff
Lots of Activity ... Two Weeks to Go !!!
Kitchen & Bath Tile ... Snow & Stuff
"Anatomy of a Mantle & Built-ins"
December 9th ... One Week to Go !!!
"Anatomy of a Fireplace" - The Conclusion
Monday, December 14th ... Two Days to Go
Tuesday, December 15th ... "One Last Thing"
"All Cleaned Up"
Wednesday, December 16th ... MOVING DAY !!!!!
Friday, December 18th ... "The Last Day" (for a while)
Merry Christmas and Happy New Year
Finally, it' Spring. The driveway gets installed.
Final Grading of the Property
Landscaping & Mulch
The Plan vs. The Finished Product
Thank You ... Thank You ... Thank You
June 26th ... Sealing the HVAC Ducts
Our new home will be built as "green" as possible, using the USGBC's (United States Green Building Council) strict guidelines. To measure our success, we will be using USGBC's LEED for Homes certification process. Under the guidelines a new home can attain Certified, Silver, Gold, or Platinum status. We are currently trying to obtain Platinum certification.